Project Team: Carter Watkins Associates Architects, Inc.
Client: City of Social Circle
Overview: This fire station is a 6,242 sqft
Features: Wood framed construction, slab on grade with brick/ siding facade. Includes staff rooms, day room, full kitchen, gear room, apparatus bay, restrooms and laundry facilities.
Duration: 8 months (completed 1 month ahead of the original construction schedule.)
Project Cost: Approx $950K
Special Notes: The site is 5.0 Acres in which 1.52 Acres were disturbed. Sunbelt Builders performed General Contracting services that included all site work, general construction, electrical, plumbing and mechanical installation.